Varun and Syan can do a work in 3 days, Syan and Anil can do it in 4 days, and Anil and Varun can do it in 6 days. How many days will Anil alone take to do the work? SSC CHSL 2021-12.04.2021-2
Working together, A, B and C can finish a piece of work in 3 hours. A finishes the same work in 8 hours and B finishes it in 6 hours. How long will it take for C alone to finish the same work? SSC CHSL 2021-12.04.2021-3
A and B can complete a certain work in 6 days and 8 days, respectively. They worked together for 3 days. C alone completed the remaining work in 2 days. B and C together can complete \(\dfrac{3}{4}\) of the same work in: SSC CHSL 2021-13.04.2021-1
A and B can complete a work in 80 days and 96 days, respectively. They completed the work in 32 days with the help of C. How many days will C take to complete the entire work alone? SSC CHSL 2021-13.04.2021-2
A can do a work in \(7\dfrac{1}{2}\) hours and B can do the same work in \(10\dfrac{1}{2}\) hours. If they work together for \(3\dfrac{1}{2}\) hours, then what part of the work will be left out? SSC CHSL 2021-13.04.2021-3